Field Progress Report 15

Work Completed

Monday 07/23/18 - Sunday 07/29/18

1. Church Expansion Scope
a. Continued brick veneer installation.
b. Gypsum board installed and sanded/finished on first and second floors.
c. Began wood trim installation on conference room glass ways and door ways.
d. Began wood trim installation on window casings.
e. Fire protection piping installed on first and second floor.
f. Conduit installed for elevator wiring.
g. Began spraying paint primer on interior walls.

2. New Parking Lot Scope
a. Demolished and removed 1508-1510 Taylor St. building and associated foundations.
b. Built new storm water inlets and placed storm water piping.
c. Installed erosion control fencing.
d. Clear remaining asphalt around old building.

3. New Nursery Scope in existing Church facility
a. Concrete slab section removed, plumbing roughed in, and concrete placed back for new bathroom.

Work Planned

Monday 07/30/18 through Sunday 08/05/18

1. Church Expansion Scope (Original Project Scope):
a. Continue painting first coat.
b. Gypsum board touch-up.
c. Begin installing ceiling grid.
d. Continue above ceiling mechanical and electrical rough in.
e. Continue wood trim installation on first and second floor.
f. Begin stair tread installation.

2. New Parking Lot Scope:
a. Continue clearing and grading.
b. Begin placing curb and gutter for sidewalks and islands.

3. New Nursery Scope in existing Church facility:
a. Frame wall and begin wall plumbing rough-in in nursery.

Field Delays

1. Day(s) Lost to Weather this Progress Report: 0 day(s)
2. Additional Day(s) Lost to Adverse Site Conditions this Progress Report: 0 day(s)
3. Total Day(s) Lost to Rain: 11 day(s)
4. Total Additional Day(s) Lost to Adverse Site Conditions: 0 day(s)