Field Progress Report 13

Work Completed

Monday 07/2/18 - Sunday 07/8/18

1. Installed main electric service wire to electrical panel and completed joints on first floor.
2. Continued installing brick veneer on Bull Street side of building.

Work Planned

Monday 07/9/18 through Sunday 07/15/18

1. Continue above ceiling mechanical.
2. Continue installing brick veneer at building corners and mortar touch up.
3. Continue hanging and finishing sheetrock.
4. Remove building and foundation at 1508/1510 Taylor Street.
5. Begin rough grading for new parking lot.
6. Continue attic modifications.

Field Delays

1. Day(s) Lost to Weather this Progress Report: 0 day(s)
2. Additional Day(s) Lost to Adverse Site Conditions this Progress Report: 0 day(s)
3. Total Day(s) Lost to Rain: 11 day(s)
4. Total Additional Day(s) Lost to Adverse Site Conditions: 0 day(s)