Field Progress Report 14

Work Completed

Monday 07/9/18 - Sunday 07/13/18

1. Continued installing brick veneer at Bull Street gables, under windows, and at building corners.
2. Installed first floor HVAC drain lines, copper lines, and duct work.
3. Set electrical circuit panel on first floor.
4. Installed exterior soffit and fascia.
5. Continued installing and finishing gypsum board.

Work Planned

Monday 07/14/18 through Sunday 07/20/18

1. Continue above ceiling mechanical installation.
2. Continue brick installation at building corners, gables, and touch up brick mortar. 3. Continue installing and finishing gypsum board.
4. Demolish building and begin clearing for new parking lot.

Field Delays

1. Day(s) Lost to Weather this Progress Report: 0 day(s)
2. Additional Day(s) Lost to Adverse Site Conditions this Progress Report: 0 day(s) 3. Total Day(s) Lost to Rain: 11 day(s)
4. Total Additional Day(s) Lost to Adverse Site Conditions: 0 day(s)