Field Progress Report 12

Work Completed

Monday 06/18/18 - Sunday 06/24/18

1. Removed scaffold from near side of building.
2. Constructed roof support modifications.
3. Installed fascia around exterior of building.
4. Installed soffit framing.
5. Started hanging and finishing gypsum board.
6. Installed wiring for lighting on first and second floor.

Work Planned

Monday 06/25/18 through Sunday 07/01/18

1. Continue above ceiling electrical rough in.
2. Continue above ceiling mechanical rough in.
3. Continue installing brick veneer.
4. Build scaffolding and set up sidewalk lane closure for Bull Street side of building.
5. Continue hanging and finishing gypsum board.

Field Delays

1. Day(s) Lost to Weather this Progress Report: 0 day(s)
2. Additional Day(s) Lost to Adverse Site Conditions this Progress Report: 0 day(s)
3. Total Day(s) Lost to Rain: 11 day(s)
4. Total Additional Day(s) Lost to Adverse Site Conditions: 0 day(s)