Field Progress Report 11

Work Completed

Monday 06/11/18 - Sunday 06/17/18

1. Started brick veneer on west side of building.
2. Continue installing attic spray foam.
3. Connected fire alarm wiring from new to existing building.
4. Started installing data wiring.
5. Set door frames on first and second floor.
6. Started pulling electrical wiring to first floor panel box.
7. Started setting attic air handlers.
8. Started running copper line sets and electrical to first floor mini-split units and air handlers.

Work Planned

Monday 06/18/18 through Sunday 06/24/18

1. Continue above ceiling electrical.
2. Continue above ceiling mechanical.
3. Continue brick veneer.
4. Start trim work on exterior portion of building.
5. Start hanging gypsum board walls.
6. Continue attic modifications.

Field Delays

1. Day(s) Lost to Weather this Progress Report: 0 day(s)
2. Additional Day(s) Lost to Adverse Site Conditions this Progress Report: 0 day(s)
3. Total Day(s) Lost to Rain: 11 day(s)
4. Total Additional Day(s) Lost to Adverse Site Conditions: 0 day(s)