Field Progress Report 9

Work Completed

Monday 05/21/18 - Sunday 05/27/18

1. Continued brick work on east side of building.
2. Ran drain lines and relocated exhaust vent.
3. Graded soil on west side to allow for scaffold to be built.
4. Shingled connector section of roof.
5. Completed spray foam insulation for the second-floor joists.

Work Planned

Monday 05/28/18 through Sunday 06/03/18

1. Continue above ceiling electrical.
2. Continue above ceiling mechanical.
3. Continue brick work.
4. Shingle the remainder of the roof.
5. Start hanging ceiling acoustical gypsum board.

Field Delays

1. Day(s) Lost to Weather this Progress Report: 1 day(s)
2. Additional Day(s) Lost to Adverse Site Conditions this Progress Report: 0 day(s)
3. Total Day(s) Lost to Rain: 11 day(s)
4. Total Additional Day(s) Lost to Adverse Site Conditions: 0 day(s)
5. Total Days Lost to Date: 0 day(s)