Field Progress Report 8

Work Completed

Monday 04/23/18 - Sunday 04/29/18

1. Completed framing punch list items.
2. Set all exterior windows.
3. Continued mechanical, electrical, and plumbing rough-in.

Work Planned

Monday 04/30/18 through Sunday 05/06/18

1. Begin laying shingles for roof.
2. Continue mechanical, electrical, and plumbing rough-in.
3. Start exterior brick work.

Field Delays

1. Day(s) Lost to Weather this Progress Report: 1 day(s)
2. Additional Day(s) Lost to Adverse Site Conditions this Progress Report: 0 day(s)
3. Total Day(s) Lost to Rain: 6 day(s)
4. Total Additional Day(s) Lost to Adverse Site Conditions: 0 day(s)
5. Total Days Lost to Date: 0 day(s)