Field Progress Report 7

Work Completed

Monday 04/9/18 - Sunday 04/15/18

1. Second floor walls framed.
2. Began installing attic subfloor.
3. Began install roof rafters, ridge/valley beams, and roof exterior sheeting.

Work Planned

Monday 04/16/18 through Sunday 04/22/18

1. Continue roof framing and dry in exterior building.
2. Start punch list items for first and second floor.
3. Beginning electrical/plumbing rough in.

Field Delays

1. Day(s) Lost to Weather this Progress Report: 0 day(s)
2. Additional Day(s) Lost to Adverse Site Conditions this Progress Report: 0 day(s)
3. Total Day(s) Lost to Rain: 5 day(s)
4. Total Additional Day(s) Lost to Adverse Site Conditions: 0 day(s)
5. Total Days Lost to Date: 0 day(s)