Field Progress Report 6

Work Completed

Monday 03/26/18 - Sunday 04/1/18

1. West side foot reworked per Geotech Engineer’s recommendation.
2. Concrete placed, sawcut and sealed for building slab.
3. Concrete formwork stripped from building slab.
4. Received lumber package delivery.

Work Planned

Monday 04/02/18 through Sunday 04/08/18

1. Begin first floor framing layout with chalk lines.
2. Begin placing interior wedge anchors.
3. Begin installing floor plates.
4. Demobilize remaining concrete crew’s equipment.

Field Delays

1. Day(s) Lost to Weather this Progress Report: 0 day(s)
2. Additional Day(s) Lost to Adverse Site Conditions this Progress Report: 0 day(s)
3. Total Day(s) Lost to Rain: 5 day(s)
4. Total Additional Day(s) Lost to Adverse Site Conditions: 0 day(s)
5. Total Days Lost to Date: 0 day(s)