Field Progress Report 5

Work Completed

Monday 03/19/18 - Sunday 03/25/18

1. Completed formwork for building slab.
2. Completed in-slab plumbing.
3. Completed excavating interior footings.
4. Sprayed termite treatment on building pad and laid vapor barrier.

Work Planned

Monday 03/26/18 through Sunday 04/1/18

1. Rework west side footing.
2. Place concrete for building slab.
3. Receive lumber package delivery.
4. Begin first floor framing.

Field Delays

1. Day(s) Lost to Weather this Progress Report: 1 day(s)
2. Additional Day(s) Lost to Adverse Site Conditions this Progress Report: 0 day(s)
3. Total Day(s) Lost to Rain: 4 day(s)
4. Total Additional Day(s) Lost to Adverse Site Conditions: 0 day(s)
5. Total Days Lost to Date: 0 day(s)