Field Progress Report 1

Work Completed

Monday 02/19/18 through Sunday 02/25/18:

  1. All asphalt removed from designated area.
  2. Power pole removed from site by SCE&G.
  3. Existing stairway removed and temporary safety railing installed.
  4. 8” storm water lines removed from under building pad.
  5. Silt fence and construction entrance installed.
  6. Began site grading and completed graded building pad.

Work Planned

Monday 02/26/18 through Sunday 03/04/18:

  1. Begin digging foundations for building slab.
  2. Begin installing under-slab plumbing and electrical.

Field Delays

  1. Day(s) Lost to Weather this Progress Report: 0 day(s)
  2. Additional Day(s) Lost to Adverse Site Conditions this Progress Report: 0 day(s)
  3. Total Day(s) Lost to Rain: 0 day(s)
  4. Total Additional Day(s) Lost to Adverse Site Conditions: 0 day(s)
  5. Total Days Lost to Date: 0 day(s)